A steel portal frame is the usual way to build a workshop, garage or light-industrial unit in the UK. It gives a clear floor with no internal columns, takes large doors easily and goes up quickly once the slab is down.
Typical workshop sizes
| Use | Span × length | Eaves height |
|---|---|---|
| Small vehicle or trade workshop | 9–12 m × 12–18 m | 4–5 m |
| Agricultural or plant repair workshop | 12–15 m × 18–24 m | 5–6 m |
| Light-industrial unit | 15–24 m × 24–36 m | 6–8 m |
Frames are usually spaced 4.5 to 7.5 m apart. Allow at least 0.5 m between the top of your tallest door and the eaves, because the haunch at each frame and the door's roll box take up that space.
Doors and openings
- Roller shutter doors sized for the largest vehicle plus about 0.5 m each side and 0.3 m above. Powered doors must meet BS EN 13241 and have safety edges or photocells to BS EN 12453.
- Sliding doors or open bays where the building doesn't need to be heated or secure.
- Personnel doors on each escape route. In a heated building, insulated steel doors are needed to meet Part L.
- Windows and rooflights for daylight. Rooflights at about 10% of the roof area give good daylight without too much heat loss.
Mezzanines and offices
A mezzanine floor at about 3 m gives office or storage space without a bigger footprint. It needs its own steelwork, a stair with handrails, and in most cases an escape route that meets Approved Document B.
Heated workshops and Part L
If the workshop will be heated, Approved Document L sets limiting U-values. Under the 2021 edition these are walls 0.26, roofs 0.18, floors 0.18, windows 1.6 and vehicle doors 1.3 W/m²K, with an air-tightness limit of 8 m³/(h·m²). Insulated composite panels (about 100 mm on walls and 120 mm on the roof) normally meet these. The Future Buildings Standard (Approved Document L 2026) applies to work after 24 March 2027.
Fire escape
Approved Document B limits how far anyone has to walk to an exit. For industrial use that is 25 m where there is only one way out and 45 m where there are alternatives. A long workshop usually needs a personnel door at each end.